Nova Scotia outlook / 5-Year Plan

 
Post new topic   Reply to topic    Clinched Highway Mapping Forum Index -> 6-Month Outlook
View previous topic :: View next topic  
Author Message
yakra



Joined: 30 Jul 2008
Posts: 2600
Location: Area Code 207

PostPosted: Wed Apr 11, 2012 8:42 pm    Post subject: Nova Scotia outlook / 5-Year Plan Reply with quote

http://www.gov.ns.ca/tran/highways/constructionprojects.asp

http://www.gov.ns.ca/tran/highways/fiveyearplan.asp
http://www.gov.ns.ca/tran/highways/5yearplan/Plan_2010-11.pdf
http://www.gov.ns.ca/tran/highways/5yearplan/Plan_2011-12.pdf
http://gov.ns.ca/tran/highways/5yearplan/Plan_2012-13.pdf

-------- 2010-11

Highway 101; Mary Jane Riley Interchange
Highway 101; Hectanooga Road Interchange Yarmouth 100 Series Expansion
Highway 104; Twinning 1 km east of Pine Tree Road to 500 m east of Route 245 (Multiple Year Project)
Highway 104; Antigonish Phase 1, 1.9 km west of Exit 31A to 0.6 km west of Exit 34, (total 7.9 km) (Multiple Year Project)
Trunk 1; Granite Drive Roundabout (including a portion of the future Highway 101 Connector, New Minas
(not in shapefiles yet, 9.0)


-------- 2011-12

Highway 101; Mary Jane Riley Interchange
Highway 104; Antigonish Phase 1, from 1.9 km west of Exit 31A to 0.6 km west of Exit 34 (total 7.9 km) (Multiple Year Project)
Highway 104; Antigonish Phase 2, from Beech Hill Road to Taylor Road, 8.0 km (Multiple Year Project)
Highway 104; Twinning 1 km east of Pine Tree Road to 500 m east of Route 245 (Multiple Year Project)

-------- 2012-13

Highway 101; Granite Dr Interchange and Connector (Multiple Year Project)
Highway 103; Port Mouton & Port Joli Bypass Broad River to Port Joli (Multiple Year Project)
Highway 103; Interchange and connector between exits 5 and 6 Phase 1 (Multiple Year Project)
Highway 104; Antigonish Phase 1, 1.9 km west of Exit 31A to 0.6 km west of Exit 34 (total 7.9 km)
Highway 104; Antigonish Phase 2, from Beech Hill Road to Taylor Road, 8.0 km (Multiple Year Project)
Highway 104; Twinning 1 km east of Pine Tree Road to 500 m east of Route 245
Highway 107; Burnside to Bedford Phase 1 (Multiple Year Project)

-------- 2013-14

Highway 101; Granite Dr Interchange and Connector (Multiple Year Project)
Highway 103; Port Mouton & Port Joli Bypass Broad River to Port Joli (Multiple Year Project)
Highway 103; Interchange and connector between exits 5 and 6 Phase 1 (Multiple Year Project)
Highway 104; Antigonish Phase 2, from Beech Hill Road to Taylor Road, 8.0 km (Multiple Year Project)
Highway 104; Taylor Road to Monastery - Paqtnkek Interchange (Multiple Year Project)
Highway 107; Burnside to Bedford Phase 1 (Multiple Year Project)
Trunk 4: from 0.2 km west of Campbell's Bridge westerly to 0.2 km west of MacNab's Bridge – 6.1 km (Multiple Year Project)
Cabot Trail (Trunk 30): from the Old Cabot Trail Road intersection northerly to LaPointe DeHavre Road – 6.4 km (Multiple Year Project)

-------- 2014-15

Highway 101; Granite Drive Interchange and Connector (Multiple Year Project)
Highway 103; Port Mouton & Port Joli Bypass Broad River to Port Joli (Multiple Year Project)
Highway 103; Interchange and connector between exits 5 and 6 (Multiple Year Project)
Highway 107; Burnside to Bedford Phase 1
(all hidden; see 2015-16)
Cabot Trail (Trunk 30): from the Little River Road southerly – 6km

-------- 2015-16

Highway 103; Interchange and connector between exits 5 and 6 (Multiple Year Project)
Trunk 4: from Soldiers Cove Road westerly to 1.8 km west
of Corbett's Cove Road - 5.2 km
Cabot Trail (Trunk 30): from Meadows Road (north end) northerly
to 1 km south of Tarbotville Road - 5.5 km

-------- 2016-17

Highway 101; Granite Drive Interchange and Connector (Multiple Year Project)
Highway 101/102 Interchange Structure & Ramp Modifications (Multiple Year Project)
Highway 103: Broad River to Port Joli, new alignment (Multiple Year Project)
• Port Mouton Bypass
• Port Joli Bypass
Highway 104: Antigonish Phase 2, from Beech Hill Road to Taylor Road, 8 km (Multiple Year Project)
Highway 104; Taylor Road to Monastery - Paqtnkek Interchange (Multiple Year Project)
Trunk 4; from 1.8 km west of Corbett's Cove Road westerly to the Canal Bridge in St. Peters - 6.2 km
Cabot Trail (Trunk 30): from Route 312 intersection northerly - 6.3 km

-------- 2017-18

Highway 107: Burnside to Bedford Phase 1 (Multiple Year Project)
Cabot Trail (Trunk 30): from 1.0 km south of Tarbotville Road northerly
to Route 312 - 4.1 km

-------- 2018-19

Projects to be determined under new Build Canada Plan


Last edited by yakra on Wed Nov 16, 2016 3:07 pm; edited 19 times in total
Back to top View user's profile Send private message
yakra



Joined: 30 Jul 2008
Posts: 2600
Location: Area Code 207

PostPosted: Sun Sep 02, 2012 2:27 pm    Post subject: Reply with quote

Construction begins on final phase of Highway 104 Antigonish bypass
Regarding Phase 1, Transport Canada wrote:
This stretch of highway will open in September 2012.
So, this is about in line with what ghYHZ said over on AARoads.
Back to top View user's profile Send private message
yakra



Joined: 30 Jul 2008
Posts: 2600
Location: Area Code 207

PostPosted: Fri Sep 07, 2012 6:46 pm    Post subject: Reply with quote

Highway project transitioning
Quote:
“All the asphalt is complete, we’re painting lines today,
...
They’re installing some jersey barrier, which is actually going to act as a noise barrier, along Trunk 7 and there are also rumble strips that still need to be installed and some signage, but we’re very close to opening.
...
The weather has been great...The roads opened early and the contractor really hasn’t lost many days due to weather, so they’re ahead of schedule as far as the opening.
Back to top View user's profile Send private message
yakra



Joined: 30 Jul 2008
Posts: 2600
Location: Area Code 207

PostPosted: Wed Sep 12, 2012 4:13 am    Post subject: Reply with quote

Minister says first phase of Antigonish highway bypass set to open
Back to top View user's profile Send private message
yakra



Joined: 30 Jul 2008
Posts: 2600
Location: Area Code 207

PostPosted: Sat Nov 24, 2012 8:48 pm    Post subject: Reply with quote

Hebbs Cross to Mill Village New 2-lane Highway
Lunenburg Co.
Route Location, Functional Design
Back to top View user's profile Send private message
Display posts from previous:   
Post new topic   Reply to topic    Clinched Highway Mapping Forum Index -> 6-Month Outlook All times are GMT - 4 Hours
Page 1 of 1

 
Jump to:  
You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot vote in polls in this forum


2005 Powered by phpBB © 2001, 2005 phpBB Group

Free Web Hosting | File Hosting | Photo Gallery | Matrimonial


Powered by PhpBB.BizHat.com, setup your forum now!
For Support, visit Forums.BizHat.com